In this Procurement UnpACked, we explore some amendments contracting authorities may want to consider adding to their contract terms and conditions in light of the Procurement Act 2023 (PA 23).
Below-threshold contracts | |
Topic / section in PA 23 | Considerations |
Implied payment terms (s 88) | Despite being implied, contracting authorities may want to ensure the following obligations are expressly included so all parties have a clear understanding of the payment obligations.
|
Procurement investigations (s 108) | Consider including an obligation on suppliers to provide information to assist any procurement investigation connected with their contract. |
Above-threshold contracts | |
Topic | Considerations |
Assessment of contract performance (s 71) | Where the public contract exceeds £5million (inclusive of VAT) contracting authorities must publish an assessment of performance on the three KPIs most material to the performance of the contract obligations at least once every 12 months during the lifetime of the contract and on termination. Consider setting out a process in which performance ratings are agreed prior to publishing / how disputes relating to performance ratings will be dealt with. |
Implied payment terms (s 68) | The same implied payment terms as set out in the “below-threshold” section above but also includes a requirement to accept invoices in electronic form. |
Sub-contracting (s 72 and 73) | Consider including an obligation on suppliers to enter into a legally binding arrangement with a sub-contractor where:
Consider also including express termination rights should the supplier/contractor fail to enter into such sub-contract. The same implied payment terms mentioned earlier apply to sub-contracts, so contracting authorities may want to expressly include these obligations to ensure the obligations flow down. |
Modifications (s 74) | Contracting authorities will be familiar with the permitted modification ground if the modification is provided for the in the contract. However, the PA 23 includes a new permitted contract modification ground of “materialisation of a known risk”. Contracting authorities may want to consider permitting known risks that were set out in the tender or transparency notice as part of any contract variation process. |
Implied termination grounds (s 78) | Despite being implied, contracting authorities may want to ensure the following termination grounds are expressly included:
|
Conflicts of interest (s 81- 83) | Contracting authorities must take all reasonable steps to identify, and keep under review, any actual or potential conflicts of interests as well as keeping conflict assessments under review. Consider including an obligation on suppliers to notify them of a conflict of interest and to provide information to enable a revised conflict assessment. |
Publishing a copy of the contract (s 53) | Contracting authorities must publish a copy of the contract where the estimated contract value is over £5million (inclusive of VAT). This must be published within 90 days of the contract being entered into or modified. Consider including an obligation on suppliers/contractors to specify what, if any, commercially sensitive information needs to be redacted prior to publication, the reasons why and what the overriding public interest is. |
Contracting authorities will need to consider whether these provisions are relevant to the contract they are procuring (i.e. the obligation to set and publish at least three KPIs does not apply to a framework, a utilities contract awarded by a private utility, a concession contract or a light touch contract).
If you would like any support amending your terms and conditions or to discuss the PA 23 contract obligations further, please contact Naomi Dowthwaite or Chanel Quigley.